Filter installation
|
Structure with two site fabricated siloses dia 5m on place. |
Under roof, 650 T of structure with 300 T of process equipment erected Dec. 2005!
|
FINAL WORKS - a part of conveyer system installed leading from storage Hall (see photos below!)
|
|
First Main Girders of Storage Hall under erection!
Start of STORAGE HALL structure erection, for Coal dry grinding plant.
|
|
(for supply of material to Mill plant).
Mill plant |
|
Storage structure erection works....
View of Storage Hall erection works from Dry Coal Grinding Plant
(on left-conveyer to Mill tower)
|
|
|
500 ton of main structure with additional 350 Ton of secondary structures of process equipment in place. |
Roof and part of conveyer to new
COAL DRY GRINDING PLANT in operation. |